Countdown Begins for Full Productivity of Azar Joint Field

The operator of Azar Joint Field Development Project said several sections of the central processing unit of the project were about to start early production. bringing the field’s output to the planned level.

According to the Petroleum Engineering and Development Company (PEDEC). Keyvan Yarahmadi said the field’s output would reach 65.000 b d soon given inauguration of the new facilities.

He said the LP and HP flares of the unit were set in motion after carrying out all the related operations including piping. mechanical section. instruments supply and pre-commissioning tests.

He said the LP flare was 37 meters high and had a 16-inch gas riser and a 28-inch air riser.

The HP flare is 72 meters high and has a 28-inch gas riser and a 42-inch air riser.

About core

Check Also

Saudi Aramco Eyes Stake in Chinese Petrochemical Firm

Saudi oil giant Aramco is proceeding with plans to boost its downstream presence in its …

Leave a Reply

Your email address will not be published. Required fields are marked *