Statoil has received consent to use West Elara for drilling and completing on the Valemon field.
Petroleum Safety Authority has given Statoil consent to use the West Elara mobile drilling facility to drill and complete production wells 34 11-B-6 and 34 11-B-16 on the Valemon field.
Planned drilling start-up is September October 2017.
Drilling operations are expected to last for 160 days.
Valemon is a gas and condensate field in the northern sector of the North Sea. just west of Kvitebjørn. The field has been developed using a fixed production platform. Production began in 2015.
West Elara is a jack-up drilling facility. delivered by Jurong Shipyard Pte Ltd in Singapore in 2011. The facility was issued with an Acknowledgement of Compliance (AOC) by the PSA in 2011.
Tags Drilling Equinor (Statoil) Europe International International Companies North Sea Norway Oilfield Technology Production
Check Also
U.S. Grants Turkey Exemption from Sanctions on Gazprombank
The United States has exempted Turkey from sanctions on Russia’s Gazprombank so that it can …