3rd South Pars Phase 13 Platform Installed

The third offshore platform of the supergiant South Pars gas field has been installed.

According to the Pars Oil and Gas Company (POGC). Platform 13A. was installed on Monday by an HL-5000 installer in the gas field.

The structure was loaded together with 13C satellite platform a while ago by using push pull method on an FLB124 barge.

`This complex and sensitive operation. after careful climate stabilization in the sea. with strict observance of safety principles was carried out in order to accelerate the production program of the field.` said Payam Motamed. operator of Phase 13 development project.

About core

Check Also

Russia’s Natural Gas Flows to Austria Rise despite OMV Cutoff

Requests from customers in Austria and Slovakia for Russian natural gas supply via Ukraine rose …

Leave a Reply

Your email address will not be published. Required fields are marked *