Executive manager of the development plan of South Pars Gas Field Phase 13 announced the installation of its last platform in the Persian Gulf.
Payam Motamed said this is the satellite platform C13, the fourth and final platform of South Pars Phase 13, which was installed on Saturday evening by meeting safety requirements and by utilizing HL5000 installer in the reservoir position of the project.
Motamed said the weight of the mega construction was 2500 tons, noting that the platform had a 98% physical progress after completion of construction operations at SADRA Iran Marine Industrial Company industrial yard, along with the main platform A13 on Sunday and Monday 20 and 21, in February with Push-Pull method carried by FLB124 vessel and shipped to the Persian Gulf and Qatar waters off the Persian Gulf.
Tags Iran IRNA News Agency Payam Motamed
Check Also
Russia’s Yamal LNG Deploys New Tanker for Barents Sea Transshipments
Yamal LNG, the plant of Russian LNG developer and exporter Novatek, has begun using the …